TELUK LAMONG TERMINAL CAPACITY DEVELOPMENT
Teluk Lamong Terminal Capacity Development costs in 2021 were Rp76.61 billion, or 33.31% of the 2021 RKAP target of Rp230 billion. Work completed included the 150x80m Container Wharf Extension Work at Teluk Lamong Terminal, and the Electrical Installation Reliability Work at Teluk Lamong Terminal.
The 150x80 container wharf extension work at Teluk Lamong Terminal, and the physical implementation of the fields has been completed 100% (one hundred percent). The main work on the 150x80m container wharf construction was completed 100% (one hundred percent) and the handover took place on December 31, 2021. So that the Teluk Lamong Terminal Container wharf can support domestic and international B/M activities, the total length of the domestic mooring is now 600 meters, and the international mooring is now 650 meters. The mooring has a capacity for anchoring four ships at once, or ships with a maximum size of 50,000 DWT. The depth of the pond in the domestic wharf reaches -11 mLWS, and international wharf reaches -14 mLWS.